Package 1: Rehabilitation of water networks in Gaza city
his package includes rehabilitation of water networks in different localities in Gaza City of a total of 9,400 m UPVC pipelines of different diameters including fittings and other necessary accessories in different affected locations in Tal AlHawa, Shajaeya, Shiekh Radwan, and Rimmal as per the damage assessment report.
Package 2: Upgrading of wastewater networks in Rafah
This package includes upgrading and construction of wastewater networks in different localities in Rafah of a total of 6,000 m UPVC pipelines of different diameters and connects 160 HH with the wastewater network in the AlForqan area.
Notes:
- Technical and financial offers strictly should be submitted in two different envelopes.
- For pricing please use the BoQ as attached Annex C and F.
- Currency of pricing is ILS
Please consider below RFP timelines:
The schedule of the RFP process is as follows:
- a) Planned RFP issue date: 02/08/21
- b)Closing date 18/08/21 (15:30 hrs)
- c)Pre-bid meeting & site visit: 08/08/21
- d)Deadline for receipt of clarification: 10/08/21
- e)Response to clarifications by UNICEF: 14/08/21
- f) Bid receipt, opening, technical+ financial evaluation + Post bid clarifications: 18/08/21 # 02/09/21
- h) Award Notice: 05/09/21
- i) Signature of contract: 07/09/21